Environmental Protection at Pirdop

Aurubis Bulgaria is the largest copper producer in southeastern Europe and the second largest company in Bulgaria. Since the Pirdop site was officially opened in 1958, mainly copper anodes, copper cathodes, and sulfuric acid have been produced from primary raw materials here.

In the last two decades, the plant has been converted into a highly modern, environmentally friendly operation. For example, following the plant’s privatization in 1997 and acquisition by Aurubis in 2008, over € 600 million has been invested so far in modernizing the processes and improving the environmental performance of the site.

Because improving environmental protection remains a very important objective, about 32 % (€ 53 million) of all investments at the site in the last five calendar years have been allocated to environmental protection projects.

In the course of the extensive modernization, two significant, state-of-the-art environmental protection facilities in particular have been built in the last several years. In November 2014, a new rainwater treatment plant was commissioned. The facility treats rain and drainage water from the 4 km² plant premises in order to continue reducing emissions to water (link: see water emissions graphic).

A new additional treatment system for secondary hood off-gases has been in operation since March 2016. The new system utilizes a modern procedure known as Sulfacid technology, which is unique in Bulgaria and in the entire copper smelting industry. This new off-gas cleaning facility further reduces the sulfur dioxide emissions and fugitive emissions from the smelting processes (link: see SO2 emissions graphic).

Aurubis assumes responsibility for environmental conservation. Protecting nature and biodiversity is part of our environmental targets, and Aurubis Bulgaria improves the habitat conditions of plants and animals and takes the initiative to rehabilitate areas by planting grasses, bushes, and trees. Defunct landfill areas on the premises are renaturated in the course of their closing. Other environmental projects to reduce emissions likewise have a positive impact on the environment. For example, a reduction in metal emissions to water improves habitat conditions in rivers.

In 2006, Aurubis Bulgaria introduced an environmental management system in accordance with the ISO 14001 standard. The last recertification and switch to the latest requirements of the standard were successfully concluded in 2018. The external audits carried out as part of the certification of the management system include a review of the environmental data, of the fulfillment of legal provisions, and of the effectiveness of the operating processes.

The Pirdop site has been part of the EU emission trading scheme since 2008 and has continuously improved its energy efficiency over the years. Aurubis Bulgaria intends to make further investments in environmental measures and energy efficiency improvements in the future as well.

Environmental Protection Pirdop - facts & figures

SO2 emissions per ton of copper output have been reduced by 96 % since 2000.

 

Dust emissions per ton of copper output have been reduced by 99.6 % since 2000.

Key factors in the reduction of emissions include:

  • a number of modernizations in both lines of the Sulfuric Acid Plant (2001-2014)
  • the replacement of the heavy oil dryer with a steam dryer (2001-2002)
  • the first (conventional) off-gas cleaning system for secondary hood off-gases (2007)
  • the new additional (Sulfacid) off-gas cleaning system for secondary hood off-gases (2016).  

 

The specific metal emissions to water per ton of copper output have been reduced by 97 % since 2000.

Key factors in the reduction of metal emissions to water include:

  • the commissioning of the second and third stages of the treatment plant for industrial wastewater (2005-2006)
  • the modernization of the wastewater system for acidic wastewater (2006-2008)
  • the modernization of the wastewater systems for domestic sewage (2010-2011) and rainwater (2012-2013)
  • the commissioning of the rainwater treatment plant (2014).

 

Environmental Protection Measures & Projects

Next steps:

  • Constructing a new facility for cooling converter slag in pots
  • Building permit received in February 2018
  • Commissioning expected in late 2019

 

Status:

  • Currently being implemented (construction of facility)

 

Next steps:

  • Installing a new sand filter in the existing treatment plant for industrial wastewater

  • Building permit expected by October 2018
  • Commissioning expected in late 2019


Status:

  • Permit procedure is underway

 

Next steps:

  • Investigation of optimization possibilities continues
  • Implementation during the next large-scale facility overhaul (Q2 2019)

 

Status:

  • Preliminary investigations are underway

 

Next steps:

  • Building permit expected for Q2 2019
  • Conclusion of renaturation expected by the end of 2020

 

Status:

  • Planning is underway

 

Environmental Protection milestones at Pirdop site

2018

Special terminal for handling and storing sulfuric acid at the Port of Burgas: A new terminal for handling and storing sulfuric acid was officially inaugurated at the Port of Burgas on the Black Sea. The entire storage capacity is 50,000 tons of sulfuric acid. Both projects (the terminal for sulfuric acid and the warehouse for copper raw materials) were implemented in cooperation with the largest private port operator in Bulgaria – BMF Port Burgas. Beide Projekte (das Terminal für Schwefelsäure und das Lager für Kupferrohstoffe) wurden in Zusammenarbeit mit dem größten privaten Hafenbetreiber Bulgariens - BMF Port Burgas - realisiert.

2018

Expansion of fayalite landfill: The first stage of the fayalite landfill expansion was completed and commissioned in May 2018. The objective of the project is to build an extension to the existing fayalite landfill that will consist of two cells with a total capacity of ca. 19.8 million tons. The cells are surrounded by soil that is protected by an insulating layer and equipped with a drainage system. Each cell will be built in eight separate stages up to the height of the existing fayalite landfill.

2017

Warehouse for copper raw materials in the Port of Burgas: A new warehouse for copper raw materials opened at BMF Port Burgas in May 2017. The warehouse has a storage capacity of 65,000 tons of copper concentrates and covers an area of 6,000 m2. The focus of this project is on improving environmental performance when it comes to protecting the air. The new facilities enable the transport and storage of copper concentrates in closed rooms. In the process, bulk material is handled without losses. The current equipment uses the best available techniques (BAT).

2017

Seveso permit issued: In August 2017, Aurubis Bulgaria successfully received the Seveso permit pursuant to Directive 2012/18/EU (Seveso-III).

2017

Closure of the third sludge landfill: Similar to the first and second sludge landfills, the third sludge landfill for sludge from wastewater and off-gas treatment was successfully closed according to plan and in conformity with all applicable environmental requirements (especially Directive 1999/31/EC). The closed landfill will now be monitored for at least the next 30 years to ensure that all restoration work was successful.

2017

Construction of the fourth sludge landfill: The fourth special landfill for sludge from wastewater and off-gas treatment was constructed and commissioned in full conformity with all relevant environmental requirements (in particular Directive 1999/31/EC).

2015

New additional treatment plant for secondary hood off-gases (Sulfacid): The new gas cleaning system (Sulfacid) was constructed and commissioned in full conformity with the best available techniques (BAT). The project makes a notable contribution to environmental protection. It uses a modern process, a technology called Sulfacid, that is unique for Bulgaria and for the entire copper smelting industry.

2014

Opening of a rainwater treatment plant: Aurubis invested a total of € 6.3 million in the treatment plant for rainwater and drainage water. The building phase extended over a year and comprised the construction of the facility with a capacity of 250 m³/h and containment basins for accumulated wastewater. To decrease emissions to water sustainably, this plant cleans the rain and drainage water from the premises, which cover a surface of 4 km². The plant conforms to the best available techniques (BAT).

2011

Investment program “Aurubis Bulgaria 2014”: The project, which had a capital expenditure volume of € 44.2 million, included environmental protection measures amounting to € 26 million. The objective of the program was to improve the environmental balance of the smelting operations, in addition to process improvements. These improvements included the expansion of the filter capacity for the concentrate drying facility, the replacement of the concentrate burner, the expansion of the smelting furnace’s cooling equipment, and the modification and increase of the waste heat boiler’s heat exchange capacity. The construction of the new additional treatment plant for secondary hood off-gases was a considerable contribution the project made to environmental protection.

2012

Use of waste materials and introduction of a new product in the portfolio: At the end of 2012, EU subsidies to Aurubis Bulgaria were approved for a project to recycle waste materials and to introduce a new product (fayalite/fine-grained iron silicate) to the portfolio. The project was financed by the EU Regional Development Fund as part of the program “Development of the Competitiveness of the Bulgarian Economy” (2007-2013) together with the Bulgarian government. The 50 % financial support is contractually guaranteed and is related to the regional development program category “Investments in Green Industries.” Among other things, the project includes the purchasing and commissioning of new equipment for copper scrap processing and a filter press for drying fayalite, which opens up additional possibilities for using this by-product.

2010

Reopening of the renovated Flotation Plant for slag: In addition to increasing the slag processing capacity, the copper recovery rate increased, which further improved the site’s resource efficiency. The best available techniques are used in the facility.

2008

Opening of new Tankhouse: The new Tankhouse operates with fully automatic equipment and uses state-of-the-art technology pursuant to the ISA 2000 standard (Australia). The process is monitored and controlled by an automatic management system (DCS 7). The total costs for building the Tankhouse amounted to € 82 million, making it the largest industrial investment in Bulgaria at that time.

2008

Construction of the third sludge landfill: The third landfill for sludge from wastewater and off-gas treatment was built and commissioned. The highest safety standards to protect the soil, surface water, and groundwater were fulfilled here as well (especially Directive 1999/31/EC).

2008

First conventional treatment system for secondary hood off-gases: In 2008, the first conventional treatment system for secondary hood off-gases was officially commissioned in full conformity with the best available techniques (BAT). The system notably reduces emissions of fine dust and sulfur dioxide. The total investment for the project amounted to € 14 million and was financed by Aurubis.

2006

Certification of the environmental management system in accordance with ISO 14001: In March 2006, the environmental management system at the Pirdop site was successfully certified by an external auditor in accordance with the ISO 14001 standard for the first time.

2005

Upgrade of Sulfuric Acid Plant: The sulfur dioxide-rich gases that form during copper concentrate smelting in the flash smelter and at the converters are cleaned, dried, and converted into sulfuric acid in the Sulfuric Acid Plant. The facility consists of two identical units that produce concentrated sulfuric acid fully automatically. This is both used internally and sold for external use.

2005

Implementation of the Directive concerning integrated pollution prevention and control (IPPC Directive): In June 2005, the plant’s environmental protection measures were recognized with a permit pursuant to the European IPPC Directive concerning integrated pollution prevention and control.

2005

Opening of the second and third stages of the treatment plant for industrial wastewater: In 2005, the second and third stages of the treatment plant for industrial wastewater were commissioned. They use a modern technology that was developed to treat industrial wastewater in a three-stage process and that guarantees adherence to the limits for water emissions.

2004

Construction of the second sludge landfill: The second landfill built especially for sludge from wastewater and off-gas treatment also fulfills all environmental requirements and the highest safety standards to protect the soil and groundwater (especially pursuant to Directive 1999/31/EC).

2004

Belgian environmental protection prize: The successful completion of the environmental remediation program in Pirdop was distinguished with the 2003/2004 Belgian environmental protection prize in the category “International Cooperation for Sustainable Development.”

2002

Construction of a fayalite landfill: A landfill was built to store fayalite, which accumulates in the flotation process. The landfill fulfills all environmental protection requirements. The first and second expansions of the landfill were completed in 2009 and 2015, respectively.

1997–2004

Environmental remediation program: The “Georgi Damyanov” smelter was operated as a state-owned company from 1958 to 1997. Due to inadequate investments in environmental protection by the Bulgarian government, there were considerable environmental impacts in the region during this time. The company was privatized in 1997 and managed by the Belgian Union Minière Group from that point. The privatization agreement included a remediation program amounting to US$ 25 million, among other things. Within the scope of this program, defunct facilities were torn down, building rubble was appropriately disposed of, and landfill areas (the sludge settling pond known as the “Blue Lagoon,” the fayalite landfill, the slag landfill) and contaminated soil were rehabilitated. In the course of the remediation program, the first stage of the treatment plant for industrial wastewater and the first landfill for sludge from wastewater and off-gas treatment were built and commissioned in 1999.

Your Contacts

Cookies

Aurubis would like to offer you the best possible service. To do this, we store information about your visit in so-called cookies. You can find detailed information about the use of cookies on this website under “Show details.” You can check or uncheck the options in the following selection bar to choose which of the different cookies you want to accept. However, you cannot deselect necessary cookies. By clicking OK, you agree to the use of cookies.

Show details

Necessary cookies help to make a website usable by enabling basic functions such as page navigation and access to secure areas of the website. The website cannot function properly without these cookies.

Necessary Cookies

Name of Cookie Function Storage period

cookie-popup

Stores whether (functional) cookies have been accepted. 24 months from setting / update

functional-cookies

Stores whether (optional) cookies have been accepted. 24 months from setting / update

AWSELB

Amazon AWS: Used when distributing user requests to the servers.

Until the end of the session

 

Preference cookies enable a website to remember information that affects the way a website behaves or looks. This information includes e.g. B. Your preferred language or the region you are in.

Preference-Cookies

Name of Cookie Function Storage period

__utma

Google Analytics: Used to differentiate between users and sessions

24 months from setting / update

__utmb

Google Analytics: Used to determine new sessions & visits. Is updated every time data is sent to Google Analytics.

30 minutes from setting / update

__utmc

Google Analytics: In the past, this cookie operated in conjunction with the __utmb cookie to determine whether the user was in a new session/visit.

Until the end of the session

__utmz

Google Analytics: Stores where the user reached the page from.

6 months from setting / update

__utmt

Google Analytics: Used to limit the request rate.

10 Minutes

 

Cookies are small text files that websites use to make users’ experience more efficient, to provide certain functions, or to enable certain analyses. This site uses different types of cookies . Some cookies are placed by third parties that appear on our sites. We have no technical influence on cookies placed by third parties.